Walkers Snackfoods, Leicester, England

Engaged as the Australian representative for this project we attended weekly meetings with vendors and reported on progress as well as implemented site requirements into the build process where possible.

We oversaw fire protection design and drawings through to approval. Then supervised the installation on the unit prior to shipping.

Using the existing P&ID we designed, drew and installed all electrical conduit, additional rinse water lines, air supply and other services bringing them back to a single point connection area, again for ease of site installation.

Using local and international resources we arranged door to door freight of the equipment utilising a Russian Antonov in an effort to expedite the delivery process and bring the equipment online sooner.

Red Rock Deli Olive Oil

As the project managers we saw this from conception to completion refining system P&ID’s, Tank Design, complete scheduling as well as management of mechanical and electrical installation through to programming completion and commissioning. This system was integrated with the existing plant and you now see the product on the shelf.

We have been involved in all aspects of Red Rock Deli installations nationally since conception

Red Rock Deli

During the installation of the Third Red Rock Deli Line nationally we were involved in all works from preparation to completion, commissioning and production.

This installation involved the reclaiming of yard space for the extension of the existing building.
An area approximately 50m x 120m was reclaimed, we relocated operational equipment including, storage silos, water heaters and chillers, Waste handling hoppers and silos, Pest control gas system and controls as well as all wall mounted services.
As this affected the entire site operations the relocation works were delicately managed alongside the site operations team to ensure any disruption to production was minimised.

Upon completion of the relocation works, Badge Construction commenced with their part of the extension for which we remained heavily involved, coordinating site and contractor movements as well as facilitating requirements ensuring the maintenance of a safe workplace for all parties involved at all times. Acting on behalf of the client we effectively worked with Badge Construction to ensure timely completion of the building to the required standard.

During this time we remained heavily involved in the equipment planning and installation scheduling working with the client and vendors to achieve a mutually beneficial result within time and budget.
Preparing to full potential all possible services connections, service loops, organising then facilitating mechanical services installation.

On building completion the major vendors completed their individual installations whilst we facilitating the interconnecting systems, services, controls.

The Entire project had a life span of over two years from concept to completion and is deemed a success at a cost of over $36mil, we are proud to have been involved.

Due to legal requirements and confidentiality photo’s posted are limited, please contact us for more information.

Grainwaves

Grainwaves, “Ride the Wave”

A largely experimental line installed in the pre-planned vacant space beside the latest Red Rock Deli Line.

This conceptual production line was formulated from many different vendors, some proven some not and brought together on site.

Our involvement with this line started at approval from where we dealt heavily with layout planning, alterations, services preparation, site liaison, fire services alterations, consultation with insurers and vendors as well as facilitating interconnecting the different vendors equipment and developing further some of the supplied experimental equipment.

Involving the erection of new rooms within the existing factory we worked with the site teams, especially closely with quality control to complete the internal erections and modifications in preparation for the equipment arrival and installation.

During the installation of equipment our role provided communications between all of the different vendors on site as well as coordinating all support labor and equipment for services connections and machinery movements.

Following through we became key stake holders in bringing one of the experimental key items of plant to an operational and safe standard.

This project has been deemed a large success being completed on time and on budget. Estimated project value is $22mil.

Due to the sensitivity of this production line, photos cannot be offered.

Blue Tongue Brewery

Located in the heart of the Central coast of New South Wales, the combined effort of Pacific Beverages recently undertook to create the huge Blue Tongue Brewery.

Contracted by the TFG 999 Joint venture, assistance was provided with site management of the mechanical installation team.

A truly magnificent building in completion, it was great just to be a part of it.

Waste Water Plant

Delivering recycled water during the times of water concern and shortage The Smiths Snackfood Company underwent a huge upgrade to reclaim up to 70% of the currently wasted water.

Our role involved the liaison between the builders, Wiley & Co the water treatment vendors Aquatec Maxcon and site in the early stages and developed into site management of Wiley & Co during construction to ensure a productive and safe partnership.

The WWT Plant was built on existing back fill which had to be sub graded and back filled then piled. Although this was all completed away from the operational factory, it was built over large in ground services pockets all live and connected. This involved a great effort from Wiley & Co to offer dynamic footing solutions, in order to continue progressing.
With the base down we facilitated additionally covering external services and connections not covered in the Vendors scope of works.

The project is complete and operational, unfortunately we had to depart before final completion to undertake the next project.